IESO LT2 Window 2: dates, rules and municipal support
When LT2 Window 2 proposals are due, what's new compared with Window 1, and why each Ontario council's support decides which projects can bid.
Updated November 21, 2026 · From public IESO and municipal records
LT2 Window 2 is the second round of the IESO's Long-Term 2 procurement, which offers 20-year contracts for new electricity supply in Ontario. The key difference from most procurements: no project on municipal land can bid without a support resolution from that council, and the councils elected on October 26, 2026 will make those decisions. [source]
Window 2 timeline
The IESO's dates are approximate and depend on Ministry direction and the final postings. [source]
| Milestone | Expected |
|---|---|
| Final LT2 Window 2 RFP and contract posted | Q1 2027 |
| Pre-engagement with each municipality | Before submission; in Window 1, at least 60 days before proposals were due |
| Final Deliverability Guidance | By July 2027 |
| Proposals due, each with municipal support | Q2/Q3 2027 |
| Contracts awarded | Q1 2028 |
| Projects in commercial operation | 2032 |
Stakeholders asked for at least 6 months between the final Deliverability Guidance and the proposal deadline. On the current schedule those two dates are close together, so the deadline may move. [source] Add the dates to your calendar: Window 2 calendar feed.
What's changing from Window 1
- A bigger energy target. The preliminary target is 1–3 TWh. It rises to cover Window 1's shortfall of about 628 GWh, left when one selected proponent didn't sign its contract. [source]
- Repowering is allowed. Existing facilities over 1 MW can rebuild or upgrade and compete for a new 20-year contract, if they meet one of two eligibility paths tied to their current contracts and years in service. [source]
- Location points. Window 1 gave rated points to Northern Ontario sites. The IESO is exploring more northern capacity, and points for projects on circuits with spare transmission capacity or a local system benefit. [source]
- Domestic content. Window 2 will likely let proponents commit to Canadian sourcing for up to a 3% reduction in evaluated price, as in the Long Lead-Time RFP. [source]
- Agricultural land. Ground-mounted solar remains barred from prime agricultural areas, and the IESO is reviewing how the Agricultural Impact Assessment applies to repowered sites. [source] [source]
What isn't changing: municipal support
The mandatory municipal support requirement applies to every Window 2 proposal, including repowering. Proponents are responsible for working with the local municipality, including on what the 2026 election means for timing, and must have the Municipal Support Confirmation before they submit. [source] A project without its municipality's support at submission isn't eligible for a contract. [source]
Developers can start talking to municipalities before the final RFP is posted. [source] In practice, that means getting on new councils' agendas in the first months of 2027. See how municipal support resolutions work and where Ontario councils stand.
How Window 1 went
The energy stream ended with 13 contracts, 12 solar and 1 wind, for 2.37 TWh a year, against a 3.0 TWh target. The capacity stream met its 600 MW target with 640 MW of battery storage in 3 contracts. Both streams were heavily oversubscribed: about 4 times in energy and 12 times in capacity. [source] See every project and its municipality: LT2 Window 1 results by municipality.
Common questions
When are LT2 Window 2 proposals due?
The IESO's July 2026 timeline puts proposal submission in Q2/Q3 2027, after the final RFP in Q1 2027. Dates are approximate until the final documents are posted.
Does LT2 Window 2 still need municipal support?
Yes. The IESO says the mandatory municipal support requirement isn't expected to change for any Window 2 proposal, including repowering. Proponents must have the Municipal Support Confirmation before they submit.
Can existing wind and solar farms bid in Window 2?
Yes, for the first time. Window 2 allows repowering of existing facilities over 1 MW that meet the IESO's eligibility paths, for new 20-year contracts.